Bowling Green Construction

On many occasions the question has been asked “What duration will be required following major operations for a green to be played upon?” and our answer remains a constant one: “When the surface is ready”, however we were given a task to provide Desborough Bowling Club with an outdoor green in readiness for the 2019 playing season.

The current site of the new Desborough Bowling Club Complex is equipped with both Indoor and Outdoor facilities. The main Contractor for undertaking and managing works were Wren Construction. Avonmore Associates Ltd were duly appointed by the main Contractor to undertake all aspects of the Outdoor Green which included the Green Construction, Automated Irrigation System and Walkway Surround.

Avonmore Associates Ltd commenced works on 23rd July 2018 followed by the sowing of Grass Seed in early September 2018 with the first sign of germination on the 20th September 2018.

Various operations have been undertaken throughout Autumn/Winter 2018/2019 and a Full Maintenance Contract is on-going for a period of 12 months. The green was delivered to the client for play to commence mid May 2019.